Tuesday, May 26, 2015

Electrical Begins

A lot more miscellaneous things have been completed.  Most of the green painted framing issues have been fixed.  The HVAC guys are done and the Electrical guys are starting.  The basement concrete slab has been poured.  Also, a few minor roofing changes have been added.

Partial roof on garage wall has been added.  More flashing around windows and roof.
Trim divider added between where brick and siding will go.  Porch columns added.

Hose bib, Gas meter connection and A/C

Couple of attic vents added.

Radon roof vent added.

Not sure what "birdboxes" are.  Couple of electrical wires added.